- Excavation: 1 Day
- Drill piers: 1 Day
- Let piers set: 2 Days
- Weekend or something
- Plumbing: 1 Day
- Lay the wafflepods and prepare formwork: 1 Day
- Pour the slab: 1 Day
So forgive me if I don't get giddy with excitement when little parts of the job that I'm waiting to have done get completed months late.
We still don't have a slab yet. What we do have is this:
Waffles.Oh and for the curious, this was the message from the plumber to the builder discussing the appropriate method for filling in the trenches.